Construction and Renovation Timelines hit fast track

View of Multi-Purpose Facility Construction from Westen Street

January 4, 2010 - Winter months have set in, but the renovation of curent facilities at Living Hope and construction of a new multi-purpose and education facilites are heating up.   Listed below are the dates and scope of renovations according to the Building Construction and Renovation teams assigned to the project.

January 4, 2010  - April, 2010

  • Renovation of current preschool rooms on 1st floor of education building

(Pre-school classes and some adult classes are affected during the January to April time frame.  For more information on the relocation of rooms, click here).

April 2010 -  Open House for church members to view renovated Holy Spirit facilities and sign or inscribe a steel I-beam to be placed in the new facilitiy symbolically “topping out” construction.

April 5, 2010  -  June, 2010

  • Children’s building renovations on 1st, 2nd and 3rd floors
  • Fellowship Hall renovations to install a new hallway connecting glass hallway with hallway in front of Fellowship Hall
  • Renovation of current Administration area

(During these portions of renovations, certain areas will be closed for Sunday traffic.  As those dates draw nearer, more specific information will be made available).

April  2010  – Living Hope formally takes possession of Holy Spirit buldings and facilities.  Current Holy Spirit Parish Hall to be renovated for High School Student Ministry.  Current Holy Spirit worship center to be removated for use as a chapel.

The Building Construction and Renovation teams will make available more specific information on all of these steps it becomes available.