September 2007 - Living Hope Congregation approves purchase of Holy Spirit Catholic Church property and facilities for $4.75 million and approves Expansion Concept.
January 2008 – Purchase of HSCC properties completed. As part of agreement, HSCC pays LHBC rent until mid-2010, when it anticipates moving to new facilities on Smallhouse Road.
Winter 2008 - Site Preparation begins for new facilities and parking construction.
June 2009 - Parking lot completed. Building pad ready for construction.
August 2009: Bids awarded and foundation work begins.
October 2009: Renovations begin on interior of existing Living Hope structure.
January 2010 – Renovations begin on current preschool rooms on 1st floor of education building.
February 2010 – Fire protection/sprinkler systems completed in adult education area and renovated preschool areas of current structures. Holy Spirit Church congregation moves to its new facilities three months ahead of original schedule.
March 2010 - Living Hope assumes complete possession of former HSCC properties. Current Parish Hall to be renovated for High School building. HSCC Parsonage to be renovated for use as Missions/Sr. Adults/Care ministries offices.
April 5, 2010 - June, 2010 - Renovations begin on 1st, 2nd and 3rd floors of Children’s Eduation Building; Closure of Fellowship Hall for renovations to install a new hallway connecting glass hallway with hallway in front of Fellowship Hall Click here for specific information on these portions of renovations and what is closed for Sunday traffic.
April 2010 – Renovations scheduled to be completed on High School Building and Missions/Sr. Adults/Care offices.
April 11, 18 & 25, 2010 - Signing of steel support beams to be placed in building as a “topping out” of construction.
May 23, 2010 2:30 pm – 4pm – Open House for renovated High School Building, Missions/Sr. Adults/Care ministries office and Chapel.
June 2010 - Renovations scheduled to begin on current Administration area.
Summer/Fall 2010 – Scheduled completion of all renovations.
January 2011 - Completion and Occupancy of new Multi-purpose and Education buildings.