Construction and Renovation Timelines hit fast track
January 4, 2010 – Winter months have set in, but the renovation of curent facilities at Living Hope and construction of a new multi-purpose and education facilites are heating up. Listed below are the dates and scope of renovations according to the Building Construction and Renovation teams assigned to the project.
January 4, 2010 - April, 2010
Renovation of [...]
Renovations Ring in the New Year!
January 3, 2010 – Renovations in the More Hope Expansion Project step up to a new level in January as construction work moves into the pre-school rooms of the oldest section of the education building. Due to the work, pre-school and adult classrooms are being relocated beginning Sunday, January 3, 2010! Work is expected to [...]
Renovation TimeLine
October 4, 2009 – Construction is underway for the More Hope Expansion with foundational work on the new buildings hampered a bit in recent weeks by extremely wet weather. A timeline has been established for renovations of existing buildings.
October 2009 - The “glass hallway” behind the Fellowship Hall will be closed for several weeks and [...]
Bid Opening Update
July 9, 2009 – Good local interest in the Living Hope Expansion/Renovation project marked a bid opening on July 7. Representatives of Living Hope’s construction manager, Wehr Constructors, are in post-bid communication with the bidders to clarify any questions or concerns about their submitted bids. The next step is for the Steering, Design and Construction teams of [...]
Building Pad Ready to Launch
June 18, 2009 – The expansion of facilities at Living Hope Baptist Church has taken another big step with the leveling of the building pad, or site of the actual new construction. Pavement now covers gravel areas not being used for construction and is available for parking (despite several delays from rainy weather this spring and summer.
The Building Expansion [...]
Construction Nears
May 30, 2009 – The final stage of pre-construction is under way! If all goes well, construction on Phase I will begin in late July or early August.
Wehr Constructors Inc. is currently seeking interest from qualified subcontractors and suppliers.
The company strongly supports and promotes local and DBE participation.
Bid packages will be available early/middle June with [...]
Letter from Pastor Jason
May 27, 2009
Dear More Hope Supporter:
Last month, the three year capital campaign “More Hope for More People” was concluded. I want to thank you for
your contribution to this God-honoring and God-inspired project. Your sacrifices have already made a difference
and will continue to make a difference in the life of Living Hope. God led us [...]
Living Hope Now Accepting Bids
Living Hope Baptist Church – New Addition & Renovation
1805 Westen Street, Bowling Green, KY 42101
Wehr Constructors, Inc. (C.M.)
Wehr Constructors is currently seeking interest from qualified subcontractors and suppliers. Wehr Constructors, Inc. strongly supports and promotes local and DBE participation. Bid packages will be available Early/Middle June with a bid date of Late June/Early July.
*To [...]
All Torn Up!
April 9, 2009 – Winter weather is FINALLY giving way to Spring and with it are signs that the More Hope Expansion project is on its way. Construction has a HUGE impact on parking at Living Hope and more changes are on the way. Work on the building pad – that’s leveling and preparing the [...]